Your panels generate power, but no subsidy has arrived? Check the connection and metering, the monthly energy balance, and the amount shown in Soliq. A Senate hearing examined delays affecting owners of solar installations.

What the monitoring found
The Senate and Yuksalish held a public hearing on 16 November. UzA reported on 17 November that monitoring covered 26 districts and cities across 13 regions. Most inspected panels worked, but grid connection, bidirectional meter installation and settlement delays were identified, alongside servicing and equipment selection problems. Agencies were tasked with preparing practical measures. This is not an announcement cancelling subsidies or introducing a new tariff.
1. Check connection and metering
Ask the regional electricity network to confirm your official connection, registered meter and both recorded volumes: imported from and exported to the grid. Inverter generation totals do not replace settlement metering. A+ and A− commonly label energy directions, but confirm their meaning for your specific meter. For discrepancies call 1154 and keep the enquiry reference.
2. Compare the same month’s volumes
Under paragraph 15 of PP-57, the household Solar Home programme pays UZS 1 000 per kWh of the positive monthly difference between grid exports and imports. For example, 500 − 200 = 300 kWh, giving a calculated subsidy of UZS 300 000. A zero or negative difference means no such subsidy for that month. Solar energy used directly at home reduces purchases but is not included in this payment. Household subsidy rules should not automatically be applied to businesses.
3. Check the amount and card transfer in Soliq
Open Soliq → Cashback and benefits → Solar Home / Quyoshli xonadon. Check the property, month, amount and card transfer section. An amount being credited and money reaching the card are separate stages. PP-57 sets payment by the 25th of the following month: October’s deadline is 25 November. As of 18 November, that deadline has not passed. Contact the Tax Committee on 1198 about subsidies.
What to include in an enquiry
State the property, account number, disputed month, imported and exported energy, and expected versus actual amount. Attach connection documents, dated meter photographs, Soliq screenshots and earlier enquiry references. Request a data check, an explanation and a written response. Send personal information through an official channel rather than public comments.
Need a new meter? Identify the cause first
Buying a meter does not itself resolve a delayed payment. If a replacement is needed, agree the model and configuration for bidirectional metering with the network. Start with Schetchik.uz’s bidirectional meter category. A “smart” label or built-in modem alone does not establish suitability.
Enquiry template
Show template
Please check the connection / metering / subsidy for [month, year], property [address], account [number]. Exported: [ ] kWh; imported: [ ] kWh. Soliq shows [ ]; the card received [ ]. Please reconcile the data, explain discrepancies, and provide the outcome and required steps in writing. Attachments: [ ]. Previous enquiry: [reference, date]. [Name, contact, date].
Frequently asked questions
Do working panels always earn a subsidy?
No. There must be a recorded positive monthly balance of grid exports minus imports.
Is all generated energy paid for?
No. Power used directly at home is excluded from this subsidy volume.
When is October’s payment due?
Under PP-57, by 25 November. On 18 November the deadline has not passed.
What if Soliq shows no amount?
Check the property, month, connection registration and energy data. Subsidies: 1198. Metering: 1154.
Who handles meter enquiries?
The regional electricity networks on 1154. Ask for a registered enquiry reference.
Will buying a new meter help?
Only if the cause is the device or its configuration. It does not guarantee payment.
Have subsidies been cancelled?
Discussion of identified problems does not cancel the programme. Check calculations against current PP-57 rules.
Should I post my account number in comments?
No. Share only the region and waiting time; send documents to the official recipient.